For stakeholders with low power and high interest, what is the recommended action?

Study for the Community Pharmacy Management Exam. Enhance your knowledge with multiple-choice questions, detailed explanations, and practical flashcards. Prepare confidently for your exam!

For stakeholders who have low power but high interest, the recommended action is to keep them informed. This approach recognizes their interest in the project or operation while acknowledging that they lack the influence to directly affect outcomes. Keeping these stakeholders well-informed helps to support transparency, build trust, and ensure that their expectations are aligned with project developments without overwhelming them with excessive information or requiring significant effort in engagement. This strategy enables them to stay engaged and feel valued, which can be beneficial for overall stakeholder relations.

In contrast, stakeholders with high power need to be managed closely to ensure their demands are met, while those with low interest and low power may only need to be monitored, given their limited stake in the project's outcome. The focus on keeping satisfied applies to stakeholders with high power and high interest, emphasizing the need to cater to their needs effectively.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy